US 96: Crews are working to plane and level up the roadway and apply a permeable friction course from Center to Tenaha. Daily lane closures expected.
 
US 84: This project to safety treat fixed objects from the Rusk County Line to US 59 is completing with clean up and vegetative establishment.
 
SH 7: Crews will continue to place a permeable friction course overlay from the San Augustine County line to Mount Hermon. Daily lane closures expected.
 
SH 87: Work continues as crews install driveway culverts and extensions through the project designed to improve guardrail to design standards and safety treat fixed objects from SH 7 to SH 147.
 
CR 4059: Crews are placing riprap at Poor Joe Creek in this bridge replacement project.
 
CR 4620: Work continues on the detour bridge along with right of way work at this bridge replacement project at Risinger Creek.
 
SAN AUGUSTINE COUNTY
 
SH 21: Work continues to replace the bridge at Perkins Creek. Daily lane closures expected.
 
SH 21: The flex base is being cement treated at this bridge replacement project over Niciper Creek.
 
FM 705: Crews are monitoring vegetative establishment on this project designed to safety treat fixed objects from SH 147 to 2.4 miles south of FM 83.
 
FM 711: Work continues to place flexible base material and mix cement on this project designed to reconstruct and widen pavement from the Shelby County line to US 96. Daily lane closures expected
 
SABINE COUNTY
 
FM 2024: Spot sealing and edge repair in various locations.
 
NACOGDOCHES COUNTY
 
SH 21: Work continues to improve guardrail to design standards and safety treat fixed objects from SH 7 to the San Augustine County line. Motorists should expect daily lane closures. A pilot car is in place to guide motorists.
 
SH 21 West: Crews will continue to mill and inlay near the Nacogdoches Courthouse at BU 59. Daily lane closures expected.
 
SH 21 East: Repairs to the road base are scheduled just east of Chireno. Lane closures expected.
 
SH 103: Work continues to upgrade metal beam guard fence to design standards from Angelina County to the San Augustine County line. Daily lane closures expected.
 
FM 95: Crews are working to drill shafts at the bridge replacement project at Terrapin Creek.
 
FM 1087: Barricades have been removed and crews are monitoring vegetative establishment on this project to safety treat fixed objects from US 259 to FM 95.
 
FM 1878: Crews are monitoring vegetative establishment and doing final cleanup on this project designed to replace the bridge at LaNana Creek.
 
POLK COUNTY
 
FM 356: Crews are installing hand rail on this project where the pavement has been reconstructed and widened with a continuous two-way left turn lane and 10-foot shoulders from 1.1 miles north of US 190 to US 190.
 
Wells Landing: Crews are monitoring vegetative establishment on this bridge replacement project.
 
 
 
 